KSEB Solar Application Guide 2026: Net Metering Step by Step

How to apply for rooftop solar and net metering with KSEB: feasibility, documents, installation, inspection, bi-directional meter and billing.

By The Solar Daily Editorial TeamPublished 2026-08-19Updated 2026-10-036 min read

Part of the complete guide: Net metering (complete guide)

Quick answer

In Kerala, small rooftop systems (reported as 1–3 kW, or up to 5 kW with a battery) use net metering, while larger systems fall under net billing, where exported units are settled at a low rate rather than your retail tariff. Apply for feasibility, sign the agreement, install via an empanelled vendor, then KSEB inspects and fits the meter. Your installer normally files the paperwork.

What net metering means for you

A bi-directional meter records the units you draw from KSEB and the units your solar sends back. Surplus units are credited against your consumption; at year-end, unused credit is settled as per KSERC rules. Because KSEB bills every two months, credits roll across billing cycles. Regulations evolve — always confirm the current KSERC regulation and KSEB circulars.

What changed in the 2025–26 KSERC rules

KSERC's newer renewable-energy regulations (effective late 2025, with billing changes from 2026) distinguish net metering for small systems from net billing for larger ones. Under net billing, exported units are settled at a low rate (reports put it around ₹2.8–3.1 per unit) instead of offsetting units you buy at the retail tariff. Time-of-day pricing and grid-support charges for larger systems have also been discussed. Existing net-metered owners are reported to keep their original terms.

Why it matters: size your system to your daytime consumption. Oversizing for export earns far less than the units you avoid buying. Confirm current limits and settlement rates with your KSEB section office; the sources we cite are trade reports, not the regulation text. See the latest Solar Daily Brief.

Documents you will need

  • Latest KSEB bill with consumer number
  • Aadhaar / ID of the consumer
  • Ownership proof or consent of owner
  • Roof layout and single-line diagram (installer provides)
  • Quotation and installer's empanelment details

Application steps

  1. Feasibility: apply online (KSEB web self-service portal) or at your Section Office; KSEB checks transformer and feeder capacity.
  2. Agreement: sign the connection agreement and pay applicable fees.
  3. Installation by an empanelled / registered vendor.
  4. Inspection: KSEB (and Electrical Inspectorate where applicable) inspects earthing, protection and anti-islanding.
  5. Meter: a bi-directional (net) meter is installed and the system is commissioned.
  6. Billing shows imports, exports and net units.

Capacity limits

The solar capacity you can connect depends on your sanctioned load, phase and the metering route above. Single-phase connections typically support smaller systems; larger ones need three-phase. Confirm with your Section Office before ordering. Installers have also reported delays in net-meter supply in some districts; see what to do if your meter is late.

Tips to avoid delays

  • Use an installer who has filed KSEB applications in your section before.
  • Ensure your bill is paid up and the consumer name matches your ID.
  • Share the PM Surya Ghar portal application number with your installer so both processes stay in sync.
Always verify. Subsidy, tariff and price figures change. Confirm with the official portal, KSEB/TNPDCL and a written quote before paying any advance. Figures here are indicative for South Kerala & Kanyakumari.

Frequently asked questions

How long does KSEB net metering take?

Typically 2–6 weeks from application to commissioning, depending on feasibility and inspection scheduling.

Does KSEB charge for net metering?

There are application and meter-related fees as per KSEB/KSERC; ask your installer for an itemised list. Be wary of unexplained 'net-metering charges'.

Can I install solar before getting KSEB approval?

Do not energise or connect to the grid before approval. Install only after feasibility to avoid penalties and subsidy delays.

What happens to my surplus units?

Surplus units are credited to future bills; unused balance at year-end is settled as per prevailing KSERC rules.