Subsidy up to ₹78,000 for homes (Tamil Nadu adds ₹22,000) · we help you claim itWhatsApp +91 62385 77759

Net metering in Kerala and Tamil Nadu: how KSEB and TNPDCL rules work in 2026

How net metering and net billing work for rooftop solar in Kerala (KSEB) and Kanyakumari (TNPDCL): limits, settlement, process, delays and how to size your system.

Pillar guideUpdated 2026-10-03By The Solar Daily Editorial Team
Quick answer

Net metering lets a bi-directional meter credit the solar units you export against what you draw. In Kerala, KSERC's 2025 regulations reportedly keep net metering for small systems (about 1–3 kW, or up to 5 kW with a battery) and use net billing for larger ones, where exports are settled at a low rate. Kanyakumari follows TNPDCL and TNERC rules. Size your system to your daytime use and confirm current limits with your section office.

What net metering means

A bi-directional meter records what you draw from the grid and what your solar sends back. Surplus units are credited against your consumption and reduce your bill. Fixed charges and duty remain, so the bill rarely reaches exactly zero. Terms are explained in the glossary.

Kerala: net metering versus net billing

KSERC's renewable energy regulations (effective late 2025, billing changes from 2026) are reported to separate small systems under net metering from larger systems under net billing. With net billing you buy units at the retail tariff and exports are settled at a low rate (reports put it around ₹2.8–3.1 per unit). Time-of-day pricing and grid-support charges for larger systems have also been reported. Existing net-metered owners are reported to keep their original terms. These details come from trade reports; confirm with your KSEB section office. See the KSEB application guide.

Tamil Nadu and Kanyakumari: TNPDCL

Grid connection and net metering in Kanyakumari follow TNPDCL and TNERC procedures. The state also gives free units to domestic consumers and has announced a ₹22,000 solar top-up. See the TNPDCL guide.

The application process

  1. Apply for feasibility with KSEB or TNPDCL.
  2. Sign the agreement and pay fees.
  3. Install through a registered vendor (do not energise yet).
  4. Inspection of earthing, protection and anti-islanding.
  5. Bi-directional meter installed and commissioning.

Meter delays

Installers reported delays in net-meter supply in parts of Kerala in August and September 2026. Keep the application number, ask the section office for dates and get your installer to state in writing who follows up. Read what to do if your net meter is late.

How to size for the rules

Under net billing, oversizing for export earns far less than the units you avoid buying. Size for your daytime use, shift loads such as EV charging and water heating to daytime, and use the calculator, which shows the net-metered option alongside the zero-bill option for Kerala.

Metering terms in plain words

TermMeaning
Net meteringOne-for-one credit: units you export offset units you import.
Net billingYou pay retail for imports; exports are paid at a set (lower) rate.
Gross meteringAll generation is sold to the utility at a tariff; you buy all your power separately.
BankingCarrying surplus credit forward to later billing periods.
APPCAverage power purchase cost, the rate used to settle some exports.
Anti-islandingInverter protection that stops exporting when the grid is down.

Illustration: how size changes the Kerala outcome

Take a home using about 480 units a month on a ₹3,500 monthly bill. Our calculator's illustrative model, which assumes the reported rules, gives two options.

3 kW (net metering)5 kW (net billing)
Net cost after ₹78,000 subsidy~₹1.1 lakh~₹2.1 lakh
Bill reduction~73%~100% of energy charges
Payback~3.5 years~5.3 years

The 3 kW option is the better investment per rupee; the 5 kW option is for those who want the bill near zero. Which is right depends on the rules in force when you apply. Model yours in the calculator.

Time-of-day pricing: shifting your loads

  • Run the washing machine, water pump and geyser during the day.
  • Schedule EV charging in sunlight hours where possible; see solar + EV.
  • Pre-cool rooms in the afternoon rather than running AC hard at night.
  • Use timers on pumps and water heaters.

Under net billing, units you use yourself during the day are worth the full tariff, while exports earn little.

Tamil Nadu: free units and net metering together

If TNPDCL gives your household the first 100 units free each bimonthly bill, solar helps only on units beyond that. A household using 400 units a month (800 per bill) has about 700 billable units per bill, so solar sized to roughly 350 units a month covers the billable part. A household using 150 units a month has far fewer billable units and a longer payback. The calculator applies this when you pick Kanyakumari. Always check the current TNERC tariff order.

Timeline: feasibility to commissioning

StepWhat to doTypical wait
FeasibilityApply online or at the section office2 weeks (reported 15-day target in Kerala)
AgreementSign and pay feesDays
InstallationRegistered vendor installs; do not energise1–3 days
InspectionDISCOM checks earthing and protection1–3 weeks
Meter and commissioningBi-directional meter installed2–6 weeks, delays reported

Checklist before you sign

  • Which metering route will my size fall under, and what is the export rate?
  • Who applies, who pays the fees, and who follows up the meter?
  • What happens to my payment if the meter is late?
  • Is my sanctioned load enough?
  • Do I keep my current terms if I add capacity later?

Questions people ask at the section office

  1. What is my application number and its current status?
  2. Is a three-phase meter available now?
  3. Which documents are still pending?
  4. When is inspection scheduled?

Keep screenshots and dates. If delay drags on, read what to do if your net meter is late.

On-grid, hybrid and outages

On-grid systems switch off during a power cut. If you need backup, choose a hybrid inverter with a battery; see on-grid vs hybrid.

Sources and how we maintain this page

Reviewed on 2026-10-03 and re-checked monthly or when a rule changes. Where a figure comes from news or trade reports, the page says so.

Always verify. Schemes, tariffs and prices change. Confirm with the official portal, KSEB / TNPDCL and a written quote.

Frequently asked questions

What is the difference between net metering and net billing?

Net metering credits exports against imports one-for-one. Net billing pays you a set rate for exports while you pay retail for imports.

Up to what size is net metering available in Kerala?

Reported as about 1–3 kW, or up to 5 kW with a hybrid inverter and battery. Confirm with KSEB.

Who handles net metering in Kanyakumari?

TNPDCL.

Can I run my system before the meter is installed?

No. Wait for the DISCOM to commission it.

Can I export more than I use?

You can, but under net billing excess exports earn little. Size to your own use.

Will my old net-metering terms change if I add panels?

Possibly. Check with the section office before expanding.

Do I need a special meter?

Yes, a bi-directional meter fitted by the DISCOM.

Is time-of-day pricing mandatory?

It has been reported for net-billing consumers; confirm for your connection.

What if KSEB rules change after I install?

Existing net-metered owners are reported to keep their terms, but confirm your own agreement.

Get your free solar savings report

Tell us your monthly bill. We'll size the system, apply the PM Surya Ghar subsidy and connect you with a verified installer — no spam, no obligation.

Get Free Quote →Try the Calculator
Free QuoteCalculator